Dear all Safety Professionals

Reference for Risk assessments

Risk level Action and timescale Defined as per BS 8800 OR OHSAS 18001

1)Trivial: No action is required and no documentary records need be kept.

2)Tolerable : No additional controls are required. A more cost-effective solution or control measure that imposes no additional cost measure may be considered. Monitoring will help ensure that the controls are maintained.

3) Moderate: Efforts should be made to reduce the risk, but the costs of preventive measures should be carefully weighed up and limited. Risk reduction measures should be implemented within a defined time period. Where the moderate risk is associated with extremely harmful consequences, it may be necessary to carry out a further assessment to determine more precisely the likelihood of harm as a basis for improved control measures.

4) Substantial: Work should not be started until the risk has been reduced. This may call for considerable resources. Where work is already in progress, urgent action should be taken.

5) Intolerable: Work should not be started or continued until risk has been reduced. If risk cannot be reduced at any cost, then work must not proceed.

Link to comment
Share on other sites

Join the conversation

You are posting as a guest. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Loading...
×
×
  • Create New...