Guest guest Posted February 28, 2001 Report Share Posted February 28, 2001 While I was in the Military we worked " short-handed " for a while and had to go to 12-hour shifts. The scedule we worked was as follows (with 4 shifts): A-B-C-D A-Shift 2 on 2 off 3 on 2 off 2 on 3 off B-Shift 2 off 2 on 3 off 2 on 2 off 3 on C-Shift (Same as A-Shift execpt as Nights) D-Shift (Same as B-Shift except as Nights) This is not perfect as you will have one week as overtime and one week short. But in the long run it all works out pretty even. Hope this helps some. Mike Stockton, AAS - EMT-P Firefighter/Paramedic/911 Dispatcher Arklatxemt@... Quote Link to comment Share on other sites More sharing options...